After pouring and finishing the slab, you should wait 24-48 hours before removing concrete forms. You can remove the formwork once the concrete has enough strength to keep it from cracking. Concrete naturally contracts as it cures, so it should pull away from the forms and make them easier to remove.

How Long to Leave Concrete Forms On?

Concrete forms are an integral part of any concrete project. They are used to shape and contain the concrete while it sets.

It is important to know how long to leave your concrete forms on in order to ensure a successful and durable concrete project.

The amount of time that you should leave your concrete forms on depends on several factors, including the type of concrete, the size of the project, and the ambient temperature.

Generally, it is best to leave the forms on for at least 24 hours, but it can be longer depending on the above factors. When using standard concrete, the forms should remain on for at least 24 hours.

This will give the concrete enough time to cure properly and form a strong bond with the forms. After 24 hours, the concrete should be hard enough that you can remove the forms without damaging the concrete.

For large concrete projects, such as driveways or patios, the forms should be left on for at least three days. This will give the concrete enough time to cure properly and form a strong bond with the forms.

After three days, the concrete should be strong enough to withstand the weight of vehicles, furniture, or other equipment. When using a fastsetting concrete, the forms should be left on